Filters
Question type

Study Flashcards

 The activity list should include the _____, an activity identifier, and a brief description of the activity.

Correct Answer

verifed

verified

 A Tracking Gantt chart is based on the percentage of work completed for project tasks or the actual start and finish dates.

A) True
B) False

Correct Answer

verifed

verified

 The technique of fast tracking can result in lengthening the project schedule.

A) True
B) False

Correct Answer

verifed

verified

 What are milestones? Describe.

Correct Answer

verifed

verified

Milestones are the most important and vi...

View Answer

 Which term is used for a significant event on a project that normally has no duration?


A) milestone
B) activity attribute
C) activity sequence
D) schedule baseline

E) B) and C)
F) All of the above

Correct Answer

verifed

verified

 Network diagrams are the preferred technique for showing activity sequencing.

A) True
B) False

Correct Answer

verifed

verified

 After working with key stakeholders to define activities and calculate their resources, what is the next process in project schedule management?


A) develop the schedule.
B) control the schedule.
C) determine their dependencies.
D) estimate the duration of activities.

E) B) and C)
F) A) and D)

Correct Answer

verifed

verified

 The critical path on a project can change as the project progresses.

A) True
B) False

Correct Answer

verifed

verified

 A dependency pertains to the sequencing of project activities or tasks.

A) True
B) False

Correct Answer

verifed

verified

 In a(n) _____ relationship, the "from" activity must start before the "to" activity can be finished.

Correct Answer

verifed

verified

 In a project schedule, the variable that has the least amount of flexibility is _____.

Correct Answer

verifed

verified

 The ultimate goal of developing a realistic project schedule is to provide a basis for monitoring project progress for the _____ dimension of the project.

Correct Answer

verifed

verified

 The critical path is the _____ path through a network diagram, and it represents the _____ amount of slack or float.


A) longest; longest
B) longest; shortest
C) shortest; longest
D) shortest; shortest

E) A) and B)
F) B) and C)

Correct Answer

verifed

verified

 One of PERT's main disadvantages is that it does not address the risk associated with duration estimates.

A) True
B) False

Correct Answer

verifed

verified

 _____ is the number of workdays or work hours required to complete a task.

Correct Answer

verifed

verified

 In project schedule management, what is the next step after defining project activities?


A) planning schedule management
B) determining their dependencies
C) controlling the schedule
D) estimating activity duration

E) B) and D)
F) None of the above

Correct Answer

verifed

verified

 Which technique involves network diagramming and is used primarily to predict total project duration?


A) Gantt chart
B) critical path analysis
C) resource breakdown structure
D) arrow diagramming method

E) A) and B)
F) C) and D)

Correct Answer

verifed

verified

 Which is one of the main outputs of estimating activity resources process?


A) project documents update
B) milestone list
C) breakdown structure
D) activity duration estimate

E) A) and C)
F) C) and D)

Correct Answer

verifed

verified

 In project schedule management, which process generates the main outputs of an activity list, activity attributes, and a milestone list?


A) sequencing activities
B) defining activities
C) resource estimating activities
D) estimating activity durations

E) A) and D)
F) A) and C)

Correct Answer

verifed

verified

 After defining project activities, the next step in project schedule management is developing the schedule.

A) True
B) False

Correct Answer

verifed

verified

Showing 21 - 40 of 99

Related Exams

Show Answer