Filters
Question type

Study Flashcards

When a politician makes a public statement that a new building will be available in two years, a(n) ________ duration has reduced the project duration.

Correct Answer

verifed

verified

imposed
Explanation: "Imposed deadlines"...

View Answer

The project direct-cost line near the normal point is usually:


A) Sloped steeply
B) Relatively flat
C) Rising
D) Falling
E) Gently sloped

F) B) and E)
G) C) and D)

Correct Answer

verifed

verified

The shortest possible time an activity can be completed realistically is called ___ time.


A) Expedited
B) Accelerated
C) Crash
D) Optimistic
E) Optimal

F) B) and E)
G) A) and B)

Correct Answer

verifed

verified

The easiest way to add more resources to a project is not to add more people, but to schedule ________.

Correct Answer

verifed

verified

overtime
Explanation: The easi...

View Answer

When the project team is salaried, which of the following is the preferred choice for accelerating project completion?


A) Assigning additional staff and equipment
B) Subcontract work
C) Schedule overtime
D) Work longer hours
E) Both C and D are preferred choices

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

What is Critical-chain (C-C) project management and why can it be of benefit to project managers?

Correct Answer

verifed

verified

C-C project management focuses...

View Answer

The president of a software company remarks in a speech that new technologically advanced software will be available in one year.This is an example of reducing project duration caused by:


A) Imposed project deadlines
B) Time to market
C) Unforeseen project delays
D) High overhead
E) Incentive contracts

F) A) and E)
G) C) and E)

Correct Answer

verifed

verified

A

The most common method for shortening project time is to


A) Subcontract activities
B) Compromise the quality
C) Add additional staff and equipment
D) Work overtime
E) Reduce the project scope

F) A) and B)
G) C) and E)

Correct Answer

verifed

verified

Crash cost is the incremental cost incurred when an activity is reduced in duration.

A) True
B) False

Correct Answer

verifed

verified

Why is the project duration with the lowest direct costs seldom the optimum duration for a project?

Correct Answer

verifed

verified

Indirect costs, those accumulating each ...

View Answer

____ costs are incurred when completing an activity in its realistically shortest time.


A) Normal
B) Reserve
C) Crash
D) Accelerated
E) Expedited

F) A) and E)
G) A) and B)

Correct Answer

verifed

verified

What is crashing and include a discussion of crash time and crash cost?

Correct Answer

verifed

verified

Crashing is shortening an acti...

View Answer

The direct costs for completing an activity as early as possible is called its ________.

Correct Answer

verifed

verified

crash cost
Explanation: The direct cost ...

View Answer

Which of the following is the most common method for shortening project time?


A) Assigning additional staff and equipment
B) Subcontract work
C) Schedule overtime
D) Reduce project scope
E) Reduce the quality

F) D) and E)
G) A) and E)

Correct Answer

verifed

verified

A

Identify options for accelerating a project schedule when resources are not constrained.

Correct Answer

verifed

verified

1.outsourcing project work, 2.scheduling overtime, 3.adding resources, 4.establish a core project team, and 5.do it twice.

Which of the following is not considered a project indirect cost?


A) Supervision
B) Consultants
C) Equipment
D) Interest
E) All of these are considered project indirect costs

F) B) and C)
G) A) and E)

Correct Answer

verifed

verified

Sometimes very high ________ costs are recognized before a project begins and reducing these costs through shorter project durations becomes a high priority.

Correct Answer

verifed

verified

overhead
Explanation: Sometimes very hig...

View Answer

One way of reducing project costs is identifying tasks that _________ can do themselves.


A) Vendors
B) Suppliers
C) Customers
D) Company employees
E) Project teams

F) B) and C)
G) All of the above

Correct Answer

verifed

verified

Crash time is the greatest time reduction possible under realistic conditions.

A) True
B) False

Correct Answer

verifed

verified

The Snapshot from Practice which detailed the Northridge earthquake demonstrated the importance of reducing a project's ______.

Correct Answer

verifed

verified

duration
Explanation: The project durati...

View Answer

Showing 1 - 20 of 94

Related Exams

Show Answer