Filters
Question type

Study Flashcards

Delicious Treats (DT) anticipated that 84,000 process hours would be worked during an upcoming accounting period when,in fact,92,000 hours were actually worked.One of the company's cost functions is expressed as follows: Y = $16PH + $640,000 where PH is defined as process hours What budgeted dollar amount would appear in DT's static budget and flexible budget for the preceding cost function? Delicious Treats (DT) anticipated that 84,000 process hours would be worked during an upcoming accounting period when,in fact,92,000 hours were actually worked.One of the company's cost functions is expressed as follows: Y = $16PH + $640,000 where PH is defined as process hours What budgeted dollar amount would appear in DT's static budget and flexible budget for the preceding cost function?   A) Choice A B) Choice B C) Choice C D) Choice D E) Choice E


A) Choice A
B) Choice B
C) Choice C
D) Choice D
E) Choice E

F) None of the above
G) C) and D)

Correct Answer

verifed

verified

Benson's fixed-overhead budget variance is:


A) $10,000 favorable.
B) $15,000 favorable.
C) $15,000 unfavorable.
D) $20,000 favorable.
E) $20,000 unfavorablE.

F) D) and E)
G) B) and E)

Correct Answer

verifed

verified

Robert Company,which applies overhead to production on the basis of machine hours,reported the following data for the period just ended: Actual units produced: 12,000 Actual variable overhead incurred: $77,700 Actual machine hours worked: 18,800 Standard variable overhead cost per machine hour: $4.50 If Robert estimates 1.5 hours to manufacture a completed unit,the company's variable-overhead spending variance is:


A) $3,600 favorable.
B) $3,600 unfavorable.
C) $6,900 favorable.
D) $6,900 unfavorable.
E) some other amount not listed abovE.

F) A) and B)
G) D) and E)

Correct Answer

verifed

verified

Bushnell,Inc.has a standard variable overhead rate of $4 per machine hour,with each completed unit expected to take three machine hours to produce.A review of the company's accounting records found the following: Actual variable overhead: $210,000 Variable-overhead efficiency variance: $18,000U Variable-overhead spending variance: $30,000F How many units did Bushnell actually produce during the period?


A) 13,500.
B) 16,500.
C) 18,500.
D) 21,500.
E) Some other amount.

F) All of the above
G) B) and C)

Correct Answer

verifed

verified

Bunnie's Bakery anticipated making 17,000 fancy cakes during a recent period,requiring 14,000 hours of process time.Each hour of process time was expected to cost the firm $11.Actual activity for the period was higher than anticipated: 18,000 cakes and 15,200 hours.If each hour of process time actually cost Bunnie $12,what process-time variance would be disclosed on a performance report that incorporated static budgets and flexible budgets? Bunnie's Bakery anticipated making 17,000 fancy cakes during a recent period,requiring 14,000 hours of process time.Each hour of process time was expected to cost the firm $11.Actual activity for the period was higher than anticipated: 18,000 cakes and 15,200 hours.If each hour of process time actually cost Bunnie $12,what process-time variance would be disclosed on a performance report that incorporated static budgets and flexible budgets?   A) Choice A B) Choice B C) Choice C D) Choice D E) Choice E


A) Choice A
B) Choice B
C) Choice C
D) Choice D
E) Choice E

F) D) and E)
G) B) and E)

Correct Answer

verifed

verified

Efficient or inefficient use of a specific component of variable overhead (e.g. ,electricity)will cause the variable-overhead efficiency variance?

A) True
B) False

Correct Answer

verifed

verified

Abbott's variable-overhead spending variance is:


A) $20,000 favorable.
B) $20,000 unfavorable.
C) $27,000 favorable.
D) $27,000 unfavorable.
E) not listed abovE.

F) A) and D)
G) B) and E)

Correct Answer

verifed

verified

The manufacturing overhead applied to Work-in-Process Inventory by a company that uses standard costing would be computed as actual hours * a predetermined (standard)overhead rate.

A) True
B) False

Correct Answer

verifed

verified

A flexible budget is appropriate for a(n) : A flexible budget is appropriate for a(n) :   A) Choice A B) Choice B C) Choice C D) Choice D E) Choice E


A) Choice A
B) Choice B
C) Choice C
D) Choice D
E) Choice E

F) A) and D)
G) D) and E)

Correct Answer

verifed

verified

What is Gourmet's budgeted total cost if its process hours equal 25,000?


A) $325,000.
B) $450,000.
C) $775,000.
D) $1,225,000.
E) Answer cannot be determined from the information provided.

F) A) and B)
G) D) and E)

Correct Answer

verifed

verified

Rich's variable-overhead efficiency variance is:


A) $10,200U.
B) $10,200F.
C) $15,300U.
D) $15,300F.
E) some other amount.

F) A) and E)
G) B) and D)

Correct Answer

verifed

verified

Which of the following statements is/are correct concerning the application of overhead in a standard costing system driven by process hours?


A) A predetermined overhead rate is allowed only for fixed overhead.
B) Overhead application is based on standard process hours allowed.
C) Overhead application is based on actual process hours incurred.
D) Only prime costs are considered to be product costs in a standard costing system.
E) Only variable overhead costs are applied to production.

F) B) and E)
G) A) and B)

Correct Answer

verifed

verified

Flexible budgets reflect a company's anticipated costs based on variations in activity levels.

A) True
B) False

Correct Answer

verifed

verified

Which of the following is not an overhead variance?


A) Variable-overhead spending variance.
B) Variable-overhead efficiency variance.
C) Fixed-overhead efficiency variance.
D) Fixed-overhead budget variance.
E) Fixed-overhead volume variancE.

F) B) and D)
G) B) and C)

Correct Answer

verifed

verified

Which of the following should have the strongest cause and effect relationship with overhead costs?


A) Cost followers.
B) Non-value-added costs.
C) Cost drivers.
D) Value-added costs.
E) Units of output.

F) B) and E)
G) A) and D)

Correct Answer

verifed

verified

Herman Company,which applies overhead to production on the basis of machine hours,reported the following data for the period just ended: Actual units produced: 13,000 Actual fixed overhead incurred: $742,000 Standard fixed overhead rate: $15 per hour Budgeted fixed overhead: $720,000 Planned level of machine-hour activity: 48,000 If Herman estimates four hours to manufacture a completed unit,the company's fixed-overhead budget variance would be:


A) $22,000 favorable.
B) $22,000 unfavorable.
C) $60,000 favorable.
D) $60,000 unfavorable.
E) some other amount.

F) B) and C)
G) A) and B)

Correct Answer

verifed

verified

A flexible budget:


A) parallels a static budget with respect to format and advantages of use.
B) is preferred over a static budget in the evaluation of performance.
C) gives management flexibility in terms of meeting budget goals.
D) can be used to compare actual and budgeted costs at various levels of activity.
E) is characterized by choices "B" and "D" abovE.

F) B) and E)
G) D) and E)

Correct Answer

verifed

verified

Which of the following elements is (are) needed in a straightforward calculation of the variable-overhead spending variance?


A) Variable overhead incurred during the period.
B) Budgeted variable overhead based on actual hours worked.
C) Standard variable overhead applied to production.
D) Elements "A" and "B" above.
E) Elements "A" and "C" abovE.

F) A) and E)
G) A) and B)

Correct Answer

verifed

verified

Briefly describe the procedures that are used to apply manufacturing overhead to production for companies that use (1)normal costing systems and (2)those that use standard costing systems.

Correct Answer

verifed

verified

In a normal costing system,overhead is a...

View Answer

The budget variance arises from a comparison of:


A) budgeted fixed overhead expenditures with budgeted fixed overhead costs.
B) actual fixed overhead costs with budgeted fixed overhead costs.
C) actual variable overhead expenditures with budgeted variable overhead costs.
D) variable overhead costs with budgeted fixed overhead costs.
E) static-budget amounts with flexible-budget amounts.

F) None of the above
G) B) and E)

Correct Answer

verifed

verified

Showing 61 - 80 of 85

Related Exams

Show Answer